An 18-storey apartment building in Bengaluru's Kudlu area developed a tilt months after receiving occupancy certificate. The builder voluntarily sought demolition approval and hired Noida Twin Towers demolition firm Edifice to raze it. The tower will be rebuilt in two years, with compensation for 49 homebuyers.
How it unfolded
12h ago
Experts advise homebuyers on checks after tower tilt
4d ago
Demolition initiated voluntarily, unlike Noida or Kochi cases
4d ago
Builder seeks demolition approval for tilted Bengaluru tower
5d ago
Builder decides to raze shaky tower after tilt discovered
What happened earlier
Latest updates
Latest
Full story →Bengaluru tilted tower: What should homebuyers check beyond the project brochure?

An 18-storey residential tower in Bengaluru developed a tilt and is being voluntarily demolished, sparking discussions on homebuyer due diligence.
Experts advise homebuyers to seek soil investigation reports and structural designs before investing, beyond just checking brochures and amenities.
The developer SNN Raj Corp attributed the tilt to an error in the geotechnical investigation report by an external agency, which interchanged borehole readings.
Selling a tilted building is prohibited by RERA in Karnataka, preventing developers from transferring risk to unsuspecting buyers.
Buyers should verify soil reports and structural designs to identify warning signs of potential structural issues in a property.
Earlier · 4d ago
Full story →Bengaluru builder to raze shaky tower 3 months after getting occupancy certificate
SNN Raj Corp will demolish an 18-floor tower at SNN Raj Etternia complex near Kudlu off Hosur Road, Bengaluru, three months after Greater Bengaluru Authority (GBA) issued an occupancy certificate for the building.
The tower tilts due to an error in the original geotechnical investigation by a consultant who interchanged critical soil readings, according to builder director Anuj Sanjay Jain.
The tower contains 49 flats; buyers were ready to move in but must wait while the builder demolishes and reconstructs the tower over the next two years.
SNN Raj Corp has sought GBA's permission to revoke the occupancy certificate for this tower and demolish it within six months, then rebuild in 18 months.
Of the project's 972 apartments across 15 towers, 822 have been handed over; the other 14 towers are unaffected.
Earlier · 3d ago
Full story →Bengaluru: 18-Storey Apartment Building Tilts Months After OC; Builder Seeks Demolition Approval