West Asia RERA Extension
Tracked across 4 sources · Updated 7h ago
The Union Housing Ministry advised RERAs to grant four-month extensions to real estate projects due to West Asia crisis supply chain disruptions. The industry welcomed this, while homebuyers demanded equal relief.
How it unfolded
19h ago
Homebuyers question extension, seek equal relief
2d ago
Centre advises RERAs to extend project deadlines by four months
What happened earlier
Latest updates
Latest
Full story →Realty industry hails govt advisory to extend project completion timeline by 4 months in view of West Asia...

Union Housing and Urban Affairs Ministry issued an advisory asking all state Real Estate Regulatory Authorities (RERAs) to grant a four-month extension in registration and completion timelines of eligible real estate projects.
The extension applies to projects affected by disruptions arising from the ongoing conflict in West Asia.
The realty industry has hailed the government advisory.
Earlier · 1d ago
Full story →Centre Advises RERA Authorities To Grant Four-Month Extension For Real Estate Projects Affected By West Asia

The Union Ministry of Housing and Urban Affairs (MoHUA) has advised state RERA authorities to grant a four-month extension to real estate projects affected by the West Asia conflict.
The advisory, issued on July 31, cites Section 6 of the RERA Act, which allows extension in cases of Force Majeure, including war, and the Department of Expenditure's classification of the situation as war.
Eligible projects are those with original, revised, or previously extended completion dates on or after February 28, 2026.
State RERA authorities may issue a common order covering all eligible projects, rather than requiring individual applications.
The move aims to provide relief to developers facing construction delays due to global supply chain disruptions.
Earlier · 1d ago
Full story →West Asia crisis: Centre advises state RERAs to extend project deadlines by 4 months; CREDAI, NAREDCO welcome move

MoHUA advised state RERAs to grant a four-month extension for project completion deadlines under Force Majeure due to the West Asia crisis.
The extension applies to projects whose completion date (original, revised, or extended) falls on or after February 28, 2026.
MoHUA recommended that RERAs issue a single order for the extension to reduce procedural delays.
CREDAI and NAREDCO welcomed the move, stating it would help developers manage supply chain disruptions.
The advisory cites Section 6 and Section 7(3) of the Real Estate (Regulation and Development) Act, 2016, allowing extension due to war as a Force Majeure event.