LocalHindustan Times

7 years on, VVCMC yet to implement NEERI-IIT suggestions to prevent flooding

in5points
  1. Vasai-Virar City Municipal Corporation (VVCMC) has not implemented NEERI-IIT recommendations to prevent flooding for 7 years after the 2018 floods.

  2. Four NEERI-IIT reports recommended building 8-10 culverts and 3 holding ponds to strengthen drainage, but not a single point was implemented.

  3. Flooding from July 4-9, 2026, reminiscent of 2018, resulted from extensive construction in Virar West's green belt, blocking natural drainage paths.

  4. VVCMC officials say necessary works require at least ₹300 crore; they submitted a ₹117.19 crore proposal to the government, still under process.

7 years on, VVCMC yet to implement NEERI-IIT suggestions to prevent flooding · in5points