IIT-B recommends diversion of rainwater flow to prevent landslides on Pune-Mumbai Expressway’s Missing Link

in5points
  1. IIT Bombay recommended diverting natural rainwater flow above the tunnel to prevent landslides on the Pune-Mumbai Expressway’s Missing Link.

  2. The MSRDC prepared a safety action plan based on IIT-B’s study using a 1,000-year rainfall return period instead of the previous 100-year assessment.

  3. Immediate measures include installing stronger wire mesh and securing loose boulders, expected within 8-10 days.

  4. Long-term measures such as major drain diversion will be done after the monsoon, taking 1-2 months.

  5. The goal is to achieve zero fatality and zero rockfall on the carriageway of the Missing Link.